Social News XYZ     

Uganda: Deputy Speaker questions delayed Mpigi – Busega road project

Uganda: Deputy Speaker questions delayed Mpigi - Busega road project
Download logo
Uganda: Deputy Speaker questions delayed Mpigi - Busega road projectDeputy Speaker Thomas Tayebwa has tasked the leadership at Uganda National Roads Authority (UNRA) to explained the delays in the completion of Mpigi-Busega Expressway.

Tayebwa on Tuesday, 07 November 2023 led a team of legislators from the Physical Infrastructure and National Economy committees on an inspection on-going construction works at Katonga Bridge and Mpigi - Busega Expressway road.

“Myself and the current Chairman of the National Economy (Hon. John Bosco Ikojo), strongly participated in the approval of the money for Mpigi - Busega Expressway project. That was around June 2016 and we expected it to be done in three years. In 2021, it should have been commissioned. We are now in 2023 and we are seeing the progress is extremely very slow,” Tayebwa said.

 

The 35km was contracted to China Civil Engineering Construction Corporation in Joint Venture with China Railway 19th Bureau Group (U) Ltd at a contract sum of Shs547.5billion.

However, addressing journalists at Buloba in Kyengera, the Deputy Speaker noted that delays to complete the critical road and unexplained deviation from the original plan is posing traffic challenges.

“We have seen no progress has been made on the side of Kibuye-Busega and the way they had designed it at that time was that Kibuye-Busega would be the one interlinking with Kampala - Entebbe Expressway and Northern Bypass," he said adding that, "if you haven't made any progress on Kibuye-Busega, then you must find a way to make this road meaningful to serve the purpose for which we were told”.

If the main goal fails, Tayebwa warned UNRA that this project will be another effort in vain.

“We were told in 2016 that it is going to reduce the time from Busega to Mpigi to only 18 minutes. Now you cannot determine the time you are going to take on that road. You can take six hours, one hour. I have ever taken around six hours on that road. When it is like a Sunday or weekend and you are coming back, you never know or when it is school visitation days,” Tayebwa added.

Hon. Dan Kimosho, the Chairperson of the Physical Infrastructure Committee noted that, "It is imperative that the contractors find nearby sources of raw materials to expedite the process”.

“There is an explanation to it especially because it is going through swamps and takes a lot of time and they get road materials from Kakiri to work on some of these swamps and they are arguing that it affects their speed. But they are saying within 48 months from now, the road will be complete and functional,” Kimosho said.
 
As a result of delayed completion of the project, Mawokota North MP, Hon. Hillary Kiyaga told journalists that locals living along the route are constantly exposed to flooding whenever it rains.

“The delay is affecting our people, for example the drainage system. Whenever they are working there has to be a drainage system but it is not yet implemented. So the more they delay, the more effects to the general public and people,” Kiyaga said.

UNRA Executive Director, Allen Kagina told the Deputy Speaker and MPs that the delays to complete the expressway was occasioned by a cocktail of geological and technical issues.

“The original alignment was going to affect the rail road. You know the Kampala-Kasese rail road also passes here and also Ugandans had built a lot on the dry ground so passing an expressway in these areas was going to affect the settlements. So we shifted onto the edge of the swamp,” Kagina explained.

Earlier, the Deputy Speaker inspected on-going works at Katonga bridge that is under re-construction and was impressed by the progress made so far.

The essence of this crossing is to divert traffic from the old condemned bridge which was in May this year washed away by floods before it was reopened to light traffic in September.  
The crossing at River Katonga acts as a gateway for cargo trucks and passenger vehicles heading to capital city and other neighbouring countries like Rwanda, Tanzania and Democratic Republic of Congo (DRC).

UNRA director of Roads and Bridges, Eng. Samuel Muhoozi said that the steel structure will be complete by Christmas this year.

 “We are calling it a temporary bridge because it is not going to stay there for good. As you have seen, we are just doing guard rails and even vehicles can pass but we don’t allow that due to safety measures in place. So within two or three weeks’ time, we shall open this road,” Muhoozi said.

Distributed by APO Group on behalf of Parliament of the Republic of Uganda.

Facebook Comments
Uganda: Deputy Speaker questions delayed Mpigi - Busega road project

About

%d bloggers like this: