By Rahul Singh
Godda (Jharkhand), June 15 (IANS/ 101 Reporters) Eastern Coalfields Limited (ECL), an undertaking of the government, has been facing opposition over its Rajmahal Opencast Coal Project (OCP) in Godda district of Jharkhand for the last six years. At the centre of the protest is Taljhari, where farmers see their lands as their only sources of livelihood.
Production at Rajmahal OCP has been badly affected due to the protests and the company is facing immense pressure to supply more coal to the power stations of NTPC Limited. Lack of production has also impacted ECL's finances.
The protest reached its peak in the second half of January this year when the ECL management and Godda district administration faced strong resistance from the villagers despite heavy police presence. The residents claim their village falls in the Scheduled Area, but ECL has a different point of view.
"We acquire land under the Coal Bearing Areas (CBA) Act. How does the PESA apply here," asks Ramesh Chandra Mohapatra, General Manager of Rajmahal project of Eastern Coalfields Limited (ECL).
Delayed implementation of the Panchayats (Extension to Scheduled Areas) Act (PESA), 1996, in Jharkhand is working against the indigenous residents of Taljhari, where ECL has been trying to acquire land to expand its mining operations.
Being a Scheduled Area due to its indigenous-majority population, Taljhari should have come under PESA, which bestows absolute powers upon gram sabhas (village councils) on several administrative matters, including land acquisition. However, since PESA is still not being implemented in Jharkhand, 27 years after the law was passed by India's Parliament, residents cannot access the benefits of the law. In March 2023, the government informed the state legislative assembly that the process to implement the law would be completed soon.
"Twenty-seven years have passed since the enactment of PESA. Yet, consecutive governments in Jharkhand have not attempted to frame rules for its implementation. Had the act been in place, gram sabha's approval would have been mandatory for all kinds of land acquisition - be it for central, state or corporate projects," tribal rights activist Dayamani Barla tells 101Reporters.
She claims the scope of land acquisition would have reduced by at least 50 per cent and that people in Taljhari would not have been struggling the way they do if PESA was in force. Social activist Emil Walter Kandulna, who had approached the Jharkhand High Court in 2021 seeking implementation of PESA, agrees. Asked about the delays, Kandulna tells 101Reporters that the state government "fears losing control over mining activities once PESA comes into force."
However, even PESA provisions are ambiguous when it comes to mining. The act stipulates that "prior recommendation of the gram sabha or panchayats at the appropriate level shall be made mandatory for grant of concession for the exploitation of minor minerals by auction."
But there are no clear provisions regarding major minerals such as coal anywhere in the PESA gazette notification. That is why ECL official Mohapatra says the Coal Bearing Areas (Acquisition and Development) Act, 1957, takes precedence when it comes to acquiring land for mining.
The CBA Act does not seek prior and informed consent of the project-affected communities or individuals. It imposes the government's will. Under Section 4(1), the Central government can take the first step for land acquisition by declaring its intention through an official notification in the government gazette. Once the declaration is published, the government will have absolute rights over those lands.
Even if the acquisitions were for other development projects of the government, the laws would have been of no help to the residents of Taljhari. The Land Acquisition, Rehabilitation and Resettlement (LARR) Act, 2013, which is activated in such cases, calls for the consent of 80 per cent owners for land acquisition for private projects. For public-private partnership projects, it is 70 per cent. However, for government projects, no such consent is required.
So, are there no specific laws to regulate outside interference in indigenous-majority areas? There are. Provisions of PESA have been embedded in the Panchayati Raj (village self-governance) system in the Scheduled Areas of Jharkhand. But they are vague and improperly implemented.
In contrast, the provisions of the CBA Act give total power to coal ventures to acquire land. Even the LARR Act is a powerful tool. Therefore, irrespective of the rules and regulations offering protection to tribals or Scheduled Areas, other well-grounded laws supersede them.
Ground realities
The authorities at present are trying to complete all formalities in Taljhari in accordance with the special powers applicable in Scheduled Areas under the Fifth Schedule of the Indian Constitution, which makes it mandatory to get clearances from the village council. A meeting of the council was organised in Taljhari on May 2, 2023 to prepare genealogies of residents to confirm land ownerships.
"Land will be acquired in a legal manner. We are preparing a genetic table to complete the formalities," says Mahagama sub-divisional officer Sourav Kumar Bhuvaniya, without divulging whether gram sabha's approval was mandatory for land acquisition. He admits that a law and order problem exists in Taljhari, which the administration is trying to address.
"We will complete the process as per the best method available under the law," Bhuvaniya asserts. On being asked whether the gram sabha procedure for land acquisition was completed, the senior most local bureaucrat, Godda deputy commissioner Jishan Qamar, did not respond.
Genealogy preparation has hit a rough patch. Many villagers complain about mistakes. "This exercise was taken up several times, after issuing notices to the gram sabha. But the villagers simply do not cooperate," says an official, speaking on the condition of anonymity.
Residents fear that cooperating with any procedure related to land acquisition can put them in harm's way. They think the authorities will produce a document suggesting that the gram sabha has approved the project, and then they will not have any legal standing to take their case forward. For the same reason, the villagers had in 2018 passed a gram sabha resolution not to provide land for coal mining and had sent a copy to the district administration.
According to Lakhan Lal Mahto, general secretary of United Coal Workers' Union, affiliated to the All India Trade Union Congress, coal mining activities in Scheduled Areas have been relatively low in Jharkhand so far. "The conflict situation in Godda district is due to the entry of the coal company into the Scheduled Area."
ECL had set a target of rehabilitating Taljhari villagers for its mining project expansion in 2021-22 but had failed. To scale up its operations and generate more revenue to offset back-to-back losses, the company is working on a strategy of operationalising discontinued/abandoned mines through a revenue-sharing model and offering more mines to private firms under the Mine Developer and Operator model.
ECL is trying to acquire land by offering jobs, land to build houses and compensation to Taljhari residents. An official with the Rajmahal project said that 22 people from 22 families that gave land for coal mining have received government jobs and the process of appointment is going on, while some people are also working on contract basis.
For every two acres (0.8 hectares) of land provided, ECL employs a member of that family. In addition, five decimals (0.0202 hectares) of land will be given for building a house. For houses located on the acquired land, compensation will be paid according to a schedule of rates by the Central Public Works Department. For agricultural lands, compensation is as per the registry rate of the village, a minimum rate set by the government for a piece of land.
But instead of compensation, residents want rules that can block land acquisition sans consent. That will require an answer to the complex question - what is stronger in law, the CBA Act or the special provisions for Scheduled Areas?
Taljhari residents' struggle to stay put will continue till this question is answered.
(Rahul Singh is a Jharkhand-based freelance journalist and a member of 101 Reporters, a pan-India network of grassroots reporters)
Source: IANS
About Gopi
Gopi Adusumilli is a Programmer. He is the editor of SocialNews.XYZ and President of AGK Fire Inc.
He enjoys designing websites, developing mobile applications and publishing news articles on current events from various authenticated news sources.
When it comes to writing he likes to write about current world politics and Indian Movies. His future plans include developing SocialNews.XYZ into a News website that has no bias or judgment towards any.
He can be reached at gopi@socialnews.xyz