The Andhra Pradesh High Court in an interim order suspended the order issued by APGENCO cancelling the contract of Navayuga Engineering Company Limited (NECL) to construct the Polavaram Hydel Power plant.
The Andhra Pradesh government through APGENCO issued a pre-closure order to the NECL on August 14 to initiate reverse tendering for the construction of the project.
The engineering company challenged the order in the High Court on Monday. Judge D.V.S.S. Somayajulu heard the arguments and reserved the order for Thursday.
https://www.thehindu.com/news/national/andhra-pradesh/ap-high-court-suspends-order-cancelling-polavaram-hydel-plant-contract/article29220462.ece
Gopi Adusumilli is a Programmer. He is the editor of SocialNews.XYZ and President of AGK Fire Inc.
He enjoys designing websites, developing mobile applications and publishing news articles on current events from various authenticated news sources.
When it comes to writing he likes to write about current world politics and Indian Movies. His future plans include developing SocialNews.XYZ into a News website that has no bias or judgment towards any.
He can be reached at gopi@socialnews.xyz
The Andhra Pradesh High Court in an interim order suspended the order issued by APGENCO cancelling the contract of Navayuga Engineering Company Limited (NECL) to construct the Polavaram Hydel Power plant. The Andhra Pradesh government through APGENCO issued a pre-closure order to the NECL on August 14 to initiate reverse tendering for the construction of the project. The engineering company challenged the order in the High Court on Monday. Judge D.V.S.S. Somayajulu heard the arguments and reserved the order for Thursday. https://www.thehindu.com/news/national/andhra-pradesh/ap-high-court-suspends-order-cancelling-polavaram-hydel-plant-contract/article29220462.ece
This website uses cookies.